Calculates the end date after a specified number of working days.
Sample Usage
WORKDAY(DATE(1969,7,20), 4, A1:A10)
WORKDAY(A2, 10)
WORKDAY(40909, 4, B2:B17)
WORKDAY(40909, 30, {40909,40924})
Syntax
WORKDAY(start_date, num_days, [holidays])
-
start_date- The date from which to begin counting. -
num_days- The number of working days to advance fromstart_date. If negative, counts backwards.- If
num_daysis not an integer, the decimal part is truncated. That is,WORKDAY(A2,1.9)is equivalent toWORKDAY(A2,1).
- If
-
holidays- [ OPTIONAL ] - A range or array constant containing the dates to consider holidays.
Notes
WORKDAYdoes not autoconvert number formats in the same way that Google Sheets does upon direct entry into cells. Therefore,WORKDAY(10/10/2000,4)is interpreted asWORKDAY(0.005,4), where the provided date is the quotient of 10 divided by 10 divided by 2000.WORKDAYcalculates the end date after a specified number of working days. To calculate the number of working days between two dates, use NETWORKDAYS.WORKDAYworks similarly toWORKDAY.INTLbut only treats Saturday and Sunday as the weekend. UseWORKDAY.INTLto use other days of the week as the weekend.
See Also
WORKDAY.INTL: Calculates the date after a specified number of workdays excluding specified weekend days and holidays.
TO_DATE: Converts a provided number to a date.
NETWORKDAYS: Returns the number of net working days between two provided days.
N: Returns the argument provided as a number.
DATEVALUE: Converts a provided date string in a known format to a date value.
DATE: Converts a year, month, and day into a date.
Examples
Returns the end date after a specified number of working days.